October 2, 2024 — The federal government gave a key approval Tuesday to an offshore wind farm in New Jersey, even as residents in the town where its power cable would come ashore worry it could go through underground toxic waste that’s still being cleaned up.
The U.S. Bureau of Ocean Energy Management approved Atlantic Shores’ plan to construct and operate an energy facility, a major milestone in moving the project forward. The project still requires a review by the U.S. Army Corps of Engineers, and several state permits, the company said.
The project, consisting of two phases, would be built between Atlantic City and Long Beach Island in southern New Jersey. It would generate 2,800 megawatts from 197 turbines, enough to power 1 million homes.