August 9th, 2019 — Construction on Vineyard Wind, a massive plan to build 84 wind turbines 14 miles south of Martha’s Vineyard, is slated to begin by Jan. 1, but regulatory snags on two different fronts have created a race against the clock for what would be the nation’s first industrial-scale offshore wind project.
In early July, the Edgartown conservation commission dealt a surprise setback to wind developers when it voted 5-1 to deny two undersea cables that would connect the turbines to mainland Massachusetts, after hearing concerns from local fishermen. On the same day, Vineyard Wind received news that the Bureau of Ocean Energy Management (BOEM) had delayed the release of the project’s final environmental impact statement (EIS). In a press release shortly thereafter, Vineyard Wind acknowledged the need to have an EIS in hand “within, approximately, the next four to six weeks.”
Now, three weeks later, Vineyard Wind has appealed the conservation commission ruling to the Massachusetts Department of Environmental Protection (DEP). Developers are awaiting that decision, along with a statement from BOEM on the EIS.
The developments are early challenges for a huge infrastructure project that lies on the frontier of a nascent, billion-dollar renewable energy industry. Further delays have the potential to jeopardize hefty tax credits, utility contracts and equipment leases dependent upon an already tenuous supply chain and construction timeline. A source close to the project said meetings with regulators are ongoing, and that the plan is still to have construction begin by the new year.