January 3, 2024 — Vineyard Wind made mixed progress on its wind farm at the end of the year, meeting one deadline while missing another. It installed the last of 62 foundations for its wind turbines, a new map shows, pounding the remaining pieces into the seafloor before a New Year deadline, when pile driving is restricted through May. But the project missed its former goal of being fully operational by 2024, and has quite a bit of work ahead in 2025.
With the foundations finished, all but three are now connected to yellow transition pieces, which will allow tower installation to proceed, according to the Dec. 30 map. But the same map shows the project still has to install 30 towers and generators, and about 120 blades. That means dozens more barge transits in and out of the Port of New Bedford with the major turbine components on board.