February 19, 2020 — A federal regulator speaking at a conference in Boston on Tuesday posted a slide suggesting Vineyard Wind would be operational in 2023, but the company itself is not saying whether its wind farm will be generating electricity by then.
Vineyward Wind originally hoped to begin construction in 2019 and have half the 800 megawatt wind farm up and running by January 15, 2022, and the remaining half a year later. That timetable was dashed when the Bureau of Ocean Energy Management put the project on hold in August 2019 to allow for a broader review of the cumulative impact of the many wind farms being proposed along the East Coast. Last week, the federal agency said its review of Vineyard Wind would be completed this December.
Jim Bennett, the program manager of the renewable energy program at the Bureau of Ocean Energy Management, gave a slide presentation at a wind energy conference sponsored by the University of Delaware that listed 2023 as the year when Vineyard Wind would be operational. He then quickly added: “Please don’t take these dates as absolutes. They’re estimates based on our regulatory programs.”
The timing issue is significant for the nation’s first large-scale wind farm. Last year, when the project was put on hold, Vineyard Wind said it needed a quick resolution of the federal environmental review or the project might collapse. Since then, the company has indicated its construction plans are moving forward, but officials have declined to comment on how they intend to overcome the many hurdles caused by the regulatory delay.