March 15, 2021 — For the second time in less than a year, and this time for much longer, Ørsted is pushing back the expected commissioning date for its Skipjack Wind Farm off the coast of Delaware.
In an announcement Feb. 26, Brady Walker, Mid-Atlantic market manager for Ørsted, said the Danish company had notified the Maryland Public Service Commission that it now expects Skipjack to achieve commercial operations by the end of the second quarter of 2026.
In April 2020, Ørsted announced it was pushing the anticipated completion date for the 120-megawatt-producing wind farm back one year, from 2022 to 2023. At the time, company officials said the reasons for that delay were because of COVID and the federal government taking longer to analyze the impacts from the build-out of U.S. offshore wind projects.