April 11, 2025 — A massive wind power project off the coast of New York blew past President Trump’s executive order to block or pause all new wind energy leasing in federal waterways — which opponents claim will destroy aquatic life and the commercial fishing industry.
Norway-based Equinor, which already had all the necessary lease and permit approvals from the feds before Trump’s January 20 executive order went into effect, confirmed that it has started construction at the site — laying rock as the foundation for the giant 54 wind turbines — 15 miles off the coast of Long Beach.
Equinor will deliver the power by connecting to Con Edison’s electric grid via a cable link from the ocean floor to the substation at the South Brooklyn Marine Terminal in Sunset Park.
The “Empire Wind 1″ project — which will power 500,000 homes — has the strong backing from both Mayor Eric Adams and Gov. Kathy Hochul, in part to help meet the goals of the ambitious state climate change law mandating 100% zero-emission electricity by 2040 and the phasing out of fossil fuels by 2050.