November 7, 2022 — A major offshore wind project in the Massachusetts pipeline “is no longer viable and would not be able to move forward” under the terms of contracts filed in May. Both developers behind the state’s next two offshore wind projects are asking state regulators to pause review of the contracts for one month amid price increases, supply shortages and interest rate hikes.
Utility executives working with assistance from the Baker administration last year chose Avangrid’s roughly 1,200-megawatt Commonwealth Wind project and a 400 MW project from Mayflower Wind in the third round of offshore wind procurement to continue the state’s pursuit of establishing cleaner offshore wind power. Contracts, or power purchase agreements (PPAs), for the projects were filed with the Department of Public Utilities in May.
But last week, Commonwealth Wind filed a motion for a one-month delay in DPU’s review, telling the state that their project can no longer move forward as planned. A one-month freeze, the developer said, “would give the parties an opportunity to evaluate the current situation facing the project and potentially agree upon changes to the PPAs, along with other measures, that could allow the project to return to viability.”
“As has been publicly reported in recent weeks, global commodity price increases, in part due to ongoing war in Ukraine, sharp and sudden increases in interest rates, prolonged supply chain constraints, and persistent inflation have significantly increased the expected cost of constructing the project. As a result, the project is no longer viable and would not be able to move forward absent amendments to the PPAs,” attorneys for Commonwealth Wind wrote in their motion.