April 28, 2020 — A pair of offshore service vessels from the Gulf of Mexico are at work off Virginia, conducting geophysical studies on a 112,800-acre federal lease where Dominion Energy and offshore wind developer Ørsted plan to build a 2,600-megawatt turbine array beginning in 2024.
Geospatial surveyors TerraSond contracted with Houma, La.-based Bordelon Marine to use the Sarah Bordelon and the Marcelle Bordelon, both 170’x36’x10’, 440.9 dwt, to start the work in mid-April in the lease area, 27 miles east of Virginia Beach.
“These surveys will provide the company with the geological, biological, and oceanographic data needed to support planning and construction in a manner that facilitates coexistence between the natural marine ecosystem and clean energy development,” Dominion Energy said in a statement issued April 27. “Ultimately, this data will support preparation of the project’s Construction and Operations Plan to be submitted to the Bureau of Ocean Energy Management (BOEM) later this year.”