August 16, 2024 — Vineyard Wind announced Thursday that it had removed the remaining pieces of the damaged blade that had been hanging from one of its turbines since the failure event on July 13.
The hanging pieces of the blade – which once measured 351 feet and weighed 55 tons before it folded and shattered last month – were removed through a “controlled cutting operation” which Vineyard Wind had previewed in its action plan released on August 11.
“While most of the debris was collected during the operation, some entered the water column before it could be recovered,” the town of Nantucket announced on Thursday following an update from Vineyard Wind officials. “Vineyard Wind has assured the town that they will maintain teams at sea, by air, and onshore on Nantucket and surrounding areas to monitor and address any additional debris that may be found.”